Friday 23 September 2016

Update on bridges 1 and 45

It's been a while since we posted an update on the bridges, but we haven't gone away. We continue to monitor all of our many charges, and repair them where work that needs doing is selected for action.

BRIDGE 1 – STATION ROAD, BROADWAY

As you may know, bridge 1 at Broadway has been hit a number of times since it was repaired 2 years ago, at least 5 times and possibly even more. 3 of the vehicles involved were skip lorries - local ones at that - and two were curtain siders. Those are the ones we definitely know of. All forced themselves under the bridge, and out the other side, leaving a trail of ripped off bolts, ruined paintwork and torn electrical conduits.

Work started on 19th September 2016, to repair the effects of the several bridge strikes, and while the team was there, to point up some damage to the wing walls as well. The basic tasks are :-
 
1.     Carry out an inspection by a Professional Engineer, working from a lorry mounted cherry picker to determine whether any serious damage had been caused. Verbal indications today are that there is none.


Bridge inspection by engineers
 2.     Raise the conduits and cables that supply power to the low headroom warning signs. The cables have been sheared off on 4 occasions despite being higher that the headroom height stated. 
 
Moving the electrical conduit
3.     Replace approximately 6 bolts and one rivet that had been sheared off.
4.     Clean and paint approximately 200 rivet and bolt heads and numerous parts of the steel structure, which had had the paintwork scraped off by the various lorry strikes. 

Paintwork repair by the Broadway gang
In addition we are taking advantage of the partial road closures to undertake the pointing of sections of wing walls, which we couldn’t afford to do when the bridge was refurbished, 2 ½ years ago. 

Wing wall repointing work

A view of the work from the Evesham side
Next week full height scaffolding will be put in place to give access the high level brickwork on the downside, Cheltenham end. We are fortunate in that the nature of the work permits us to do the repairs one side at a time.

BRIDGE 45 – SWINDON LANE, CHELTENHAM

At the other end of the line, our regular inspections of all our structures has revealed that work now needs doing to Swindon Lane bridge.
This bridge, number 45, is located south of Hunting Butts tunnel, where Swindon Lane crosses the line as it enters a cutting. At the other end of this cutting, the trackbed begins to touch Pittville Park, and that is the end of the actual trackbed that we own. Even though we don't run any trains down this last stretch of under a mile, we continue to be responsible for the bridges.

Swindon Lane bridge looking south
A very small but vital task was carried out on this bridge last week. The bridge is constructed from 6 main steel girders running parallel with the road, and between these the gaps are filled with long panels of Jack arch brickwork. This brickwork is then covered with concrete to form a level surface, which is waterproofed with asphalt before the road materials are laid on top. The arch brickwork naturally has a sidewards thrust, which tends to push the main girders apart. This is prevented by the use of horizontal tie bars which link them all together. Unfortunately 4 of these tie bars had corroded right through and were missing, and another 3 had reduced from 7/8” diameter to less than ½” diameter. 

Arches held in place by girders tied together
 




The work required was to replace the missing ones and also remove and replace the downgraded ones.
 






Cut out for a new tie bar



Several of these passed through the very tough Jack arch brickwork, which had to be cut out and made good.

Corrosion on the girders themselves is also evident.






New tie bar inserted






A cherry picker was hired in to survey and repair the corrosion.

The cherry picker enabled Alastair Watson (of drainage gang fame) to take these pictures for us.










New tie bar in place.


Finally, a picture of the bridge looking north towards Hunting Butts and CRC. The concrete bridge in front carries the footpath, as the original bridge is on the narrow side and carries traffic far heavier than imagined in 1906.
There is a weight restriction on it.

If you are interested in this piece of our trackbed, you can see more photographs of it here:

16 comments:

  1. perhaps a yard, or better still a halt could be set up at the end of the line with a simple loop so passengers can enjoy the full tow tunnel experience

    ReplyDelete
  2. I hope that the culprits are being invoiced for these repairs?

    ReplyDelete
    Replies
    1. Invoicing and getting the money is two different things.
      We have submitted claims with identified culprits.

      Delete
  3. Guys, will you please give your names when commenting under the 'Anonymous' option.

    Thank you.

    ReplyDelete
  4. Thank you for your reply Jo I hope the identified culprits pay up.

    ReplyDelete
  5. To minimise large vehicles hitting the bridge, what about having a volunteer(s) on 'bridge duty'? They would watch the vehicles coming towards the bridge. If too high, they would show a plakard with 'Vehicle too high' on. Then if the vehicle would hit the bridge ,they can note down the index.
    What are the local Police doing about it? More patrols?
    Aaron

    ReplyDelete
    Replies
    1. I think CCTV might be a potentially less conflict answer.

      Delete
    2. Sorry. That should have read confrontorial NOT conflict. Paul.

      Delete
  6. What about a sacrificial structure like Railtrack have installed in Hyde Lane?

    ReplyDelete
    Replies
    1. Well it has my vote.
      But I also came across Blackthorne Bridge today, near Bicester on the A41.
      It was recently equipped with sensors on poles a distance away, to trigger what I presume are warning lights/messages. Apparently, the number of strikes has reduced dramatically.

      Delete
  7. How about digging the road up and exavating deeper and regrading the road lower

    ReplyDelete
  8. Surely this must be driving without due care and attention, a criminal act?

    ReplyDelete
  9. Small point but I note that 4.4 metres is slightly over 14' 5" ie 2" more than the sign says - which is correct?

    ReplyDelete
  10. Do you have any fibre optics cables buried along the line and over the bridges. You could then at least use theses to at least record every incident and you would know the exact time, location and severity.
    Alan

    ReplyDelete
  11. On that thorny topic of bridge bashes a reliable source tells us the Big Boys use conventional navigation aids that take no account of the location of low road under rail structures.
    In an ideal world we could install metal tubing set in concrete well ahead of masonry and or steel holding the bridges in place. Looking a bit like a heavy duty goalpost.
    I could help fund that. Ask me nicely.

    ReplyDelete